|
|
|
ROOM PLASTERING CONTINUES, WING JOISTS HOISTED INTO
PLACE
Poplar Forest Newsletter, Fall 2003

Mason pulls a screed over the second layer
of plaster in the northwest chamber to level it. |
Masons made good progress on wall plastering inside the
main portion of Jefferson’s retreat, while wing restoration continues apace
with the installation of giant timbers that set the stage for re-creating
Jefferson’s flat roof.
Inside the octagonal portion of the house, masons have
applied lime plaster on the walls in two spaces: the northwest chamber adjacent
to the entranceway, and half of Jefferson’s bedchamber. They
will tackle the second half of Jefferson’s chamber and the cube room
next.
In keeping with Jefferson’s original construction
sequence, the wall plastering follows last year’s ceiling plastering. Prior to
the plastering, carpenters installed the “grounds” for bases, chair rails,
entablatures, and fireplaces, and around every door and window. These plain
boards initially level the surface
of the plaster and later serve as the base for attaching finished trim.
Staff carpenters can now sympathize with their original
counterparts. Jefferson had the grounds in one room taken down and re-applied
because they were “out of plumb.” Getting the new grounds plumb on an
undulating brick walls is a necessary but time-consuming task that results in a
quality plaster job. |
Per Poplar Forest’s mission of educating visitors about
the restoration itself, the public has an good view of the plastering. Though
the rooms being worked on are enclosed in temporary walls to prevent plaster
dust from spreading throughout the house, plastic windows enable visitors to see
work in progress.
Likewise, the public had a good view of the wing’s
framing as carpenters hoisted 43 gutter joists in place that span the width of
the wing and weigh about 300 pounds each. The joists rest on large timbers
called plates that are set on top of the brick walls of the wing.
About one-half of the poplar plates are original to the
wing, having been re-used in the post-Jefferson 1840s buildings that had been
created from two wing rooms. The “new” poplar plates are also from
Jefferson’s time, coming from one of the large poplar trees salvaged from the
north lawn in 1999.
Shortly, the carpenters will begin carving grooves in the
joists to create gutters to drain the wing’s flat roof, just as in
Jefferson’s time. Subsequently, ridge joists will be placed between each
gutter joist. That handcraft is estimated to continue through the winter months.
After that, the next step in reconstructing Jefferson’s unusual flat
“terras” roof design will be to install the pine shingles linking the ridge
and gutter joists.
|
|